Name
Start
End
Milestone
%
Resources
Notes
PROJECT INITIATION27/03/202531/07/2025 0

                    
Greatech PO 250844727/03/202527/03/2025 100Greatech Purchaser

                    
Payment for PO 250844707/04/202507/04/2025 100Greatech Purchaser

                    
Gorbel Production & Assembly08/04/202523/06/2025 0Bernard Loh - Project Manager, Darren How - Project Coordinator, Muhammad Imran Hafiz - Engineer, Jacky Chen - Engineer, Gorbel Production & Design Team

                    
Confirmation of Plan & Design08/04/202510/05/2025 0Bernard Loh - Project Manager, Justin - Engineer, Muhammad Imran Hafiz - Engineer, Jacky Chen - Engineer, Gorbel Production & Design Team

                    
Workstation11/05/202507/06/2025 0Jacky Chen - Engineer, Gorbel Production & Design Team

                    
Telescopic11/05/202523/06/2025 0Jacky Chen - Engineer, Gorbel Production & Design Team

                    
Hoist08/04/202508/06/2025 0Jacky Chen - Engineer, Gorbel Production & Design Team

                    
UniqTrans Pick Up & Shipment24/06/202515/07/2025 0Bernard Loh - Project Manager, Darren How - Project Coordinator, Justin - Engineer, Puspa - Logistics

                    
Kastam Clearance16/07/202529/07/2025 0Bernard Loh - Project Manager, Darren How - Project Coordinator, Justin - Engineer, Puspa - Logistics

                    
Transportation from warehouse to BK430/07/202531/07/2025 0Bernard Loh - Project Manager, Darren How - Project Coordinator, Puspa - Logistics

                    