Name
|
Start
|
End
|
Milestone
|
%
|
Resources
|
Notes
|
| PROJECT INITIATION | 27/03/2025 | 31/07/2025 | | 0 | |
|
| Greatech PO 2508447 | 27/03/2025 | 27/03/2025 | | 100 | Greatech Purchaser |
|
| Payment for PO 2508447 | 07/04/2025 | 07/04/2025 | | 100 | Greatech Purchaser |
|
| Gorbel Production & Assembly | 08/04/2025 | 23/06/2025 | | 0 | Bernard Loh - Project Manager, Darren How - Project Coordinator, Muhammad Imran Hafiz - Engineer, Jacky Chen - Engineer, Gorbel Production & Design Team |
|
| Confirmation of Plan & Design | 08/04/2025 | 10/05/2025 | | 0 | Bernard Loh - Project Manager, Justin - Engineer, Muhammad Imran Hafiz - Engineer, Jacky Chen - Engineer, Gorbel Production & Design Team |
|
| Workstation | 11/05/2025 | 07/06/2025 | | 0 | Jacky Chen - Engineer, Gorbel Production & Design Team |
|
| Telescopic | 11/05/2025 | 23/06/2025 | | 0 | Jacky Chen - Engineer, Gorbel Production & Design Team |
|
| Hoist | 08/04/2025 | 08/06/2025 | | 0 | Jacky Chen - Engineer, Gorbel Production & Design Team |
|
| UniqTrans Pick Up & Shipment | 24/06/2025 | 15/07/2025 | | 0 | Bernard Loh - Project Manager, Darren How - Project Coordinator, Justin - Engineer, Puspa - Logistics |
|
| Kastam Clearance | 16/07/2025 | 29/07/2025 | | 0 | Bernard Loh - Project Manager, Darren How - Project Coordinator, Justin - Engineer, Puspa - Logistics |
|
| Transportation from warehouse to BK4 | 30/07/2025 | 31/07/2025 | | 0 | Bernard Loh - Project Manager, Darren How - Project Coordinator, Puspa - Logistics |
|