Name
|
Start
|
End
|
Milestone
|
%
|
Resources
|
Notes
|
| PROJECT INITIATION | 24/01/2025 | 28/03/2025 | | 0 | |
|
| PO 72560, 72661,72707 | 24/01/2025 | 24/01/2025 | | 100 | DPEM Procurement Dept |
3 PO date recieved via email
|
| Place order to Gorbel | 10/02/2025 | 10/02/2025 | | 100 | Darren How - Project Coordinator |
Due to CNY, order received from Daihatsu unable to place order to Gorbel due to 2 weeks holiday .
|
| Gorbel Production & Assembly | 10/02/2025 | 15/05/2025 | | 80 | Bernard Loh - Project Manager, Jacky Chen Engineer, Mohd Izzuddin - Engineer, Zhou (Designer EOAT) |
20 days for production and assembly
Including test of EOAT attachment to Easy Arm
|
| EasyArm | 19/03/2025 | 16/04/2025 | | 100 | Bernard Loh - Project Manager, Darren How - Project Coordinator, Jacky Chen Engineer |
|
| Tooling Design | 02/04/2025 | 25/04/2025 | | 100 | Bernard Loh - Project Manager, Jacky Chen Engineer, Mohd Izzuddin - Engineer, Zhou (Designer EOAT) |
|
| Tooling Production | 28/04/2025 | 15/05/2025 | | 0 | Bernard Loh - Project Manager, Darren How - Project Coordinator |
|
| UniqTrans Pick Up & Shipment | 17/04/2025 | 08/05/2025 | | 90 | Ms Puspa - Forwarder |
|
| MIti & Kastam Clerance | 09/05/2025 | 19/05/2025 | | 0 | Bernard Loh - Project Manager, Clearance KASTAM, Darren How - Project Coordinator |
|
| Transport to DPEM | 20/05/2025 | 21/05/2025 | | 0 | |
|
| Uniqtrans Pick Up & Shipment | 19/05/2025 | 06/06/2025 | | 0 | |
|
| Kastam Clearance | 09/06/2025 | 17/06/2025 | | 0 | |
|
| Transport to DPEM | 18/06/2025 | 19/06/2025 | | 0 | |
|
| Installation Of Easy Arm | 20/06/2025 | 23/06/2025 | | 0 | Bernard Loh - Project Manager, Jacky Chen Engineer, Simon - Installer |
|